LHC Machine Advisory Committee Meeting no. 16
Provisional - speakers to be confirmed
       
Open session, Building 30, Auditorium (7th floor)
       
       
Time Duration Speaker Subject
Thursday 09/12/04    
14:00 00:05 M. Tigner Introductory remarks
14:05 00:50 L. Evans Current status of LHC project
14:55 00:10   Questions
15:05 00:25 R. Saban Hardware Commissioning Report on Resources
15:30 00:10   Questions
15:40 00:15   Tea
15:55 00:30 R. Assmann Collimation, latest developments  LHC Collimation Review
16:25 00:00
16:25 00:10   Questions
16:35 00:40 B. Goddard Machine Protection at Injection
17:15 00:10   Questions
17:25     End of session
19:00   Dinner 
Closed session, Building 30, Room 7-012
Friday 10/12/04    
08:30 00:50 R. Assmann Collimation, optical imperfections, cleaning dynamics LHC Collimation Review
09:35 01:20 R. Schmidt Machine protection for Circulating Beam
10:55 00:35 N. Hilleret Electron Cloud update
11:30 00:00   Coffee
11:30 00:45 O. Bruning Requirements in ramp
12:15 00:30 L. Bottura Corrector settings from magnet measurements
12:45 00:00   Reserve
12:45     Lunch/Executive session
14:00 00:50 M. Nessi Visit ATLAS cavern
14:50 00:50 P. Collier Operational procedures, implementation
15:40 00:15 M. Harrison Report from Cost & Schedule Review
15:55 00:15   Tea
16:10 00:00 L. Rossi Spare magnets
16:10 01:20   Executive session
17:30   End
     
Closed session, Building 61, Salle B
Saturday 11/12/04
08:30 00:00 Reserve
08:30 01:30 Executive session
10:00 01:30   General discussion and summing up
11:30 End of session